Numbers
Every figure quoted on a call, shown exactly as it was spoken. 194 claims in this window — the place to check what uptime, recovery times, or dollar amounts we have actually committed to out loud.
All 194Duration57Count23Outage Duration23Date16Effort14Money11Response Time9Account Count8Percentage8People Count7Recovery Time5Threshold5Event Count3Throughput3Data Volume1Uptime1Flagged inconsistent14?The model recorded a note where a figure appeared to conflict with something else said on the same call.
| What was claimed | As spoken?The value exactly as it was spoken on the call, not a parsed number. | Metric | Stated by | Account | Call | |
|---|---|---|---|---|---|---|
| Derek's target completion date before internal compliance review Sofia projected early July, which is earlier. | “end of July at the latest” | Date?A specific calendar date or clock time, including deadlines, launch dates, and target dates. | Derek Owens | Crestline Wealth | Aegis / Crestline Wealth - Identity Mod… 24 Apr 2026 | |
| Sofia's projected full deployment date Earlier than Derek's end-of-July target. | “early July range” | Date?A specific calendar date or clock time, including deadlines, launch dates, and target dates. | Sofia Petrov | Crestline Wealth | Aegis / Crestline Wealth - Identity Mod… 24 Apr 2026 | |
| Next internal compliance review timing | “August” | Date?A specific calendar date or clock time, including deadlines, launch dates, and target dates. | Derek Owens | Crestline Wealth | Aegis / Crestline Wealth - Identity Mod… 24 Apr 2026 | |
| Deadline for the SOC 2 Type II report | “end of May” | Date?A specific calendar date or clock time, including deadlines, launch dates, and target dates. | Diana Reeves | Internal | SOC 2 Type II - Final Review 20 Apr 2026 | |
| Comply v2 general availability date | “April 7th” | Date?A specific calendar date or clock time, including deadlines, launch dates, and target dates. | Maria Santos | Ironworks Corp | Aegis / Ironworks Corp - Vendor Compari… 14 Apr 2026 | |
| QSA assessment scheduled date | “end of June” | Date?A specific calendar date or clock time, including deadlines, launch dates, and target dates. | Gerald Hutchins | Forge Industries | Aegis / Forge Industries - PCI DSS Comp… 9 Apr 2026 | |
| Comply v2 general availability date | “April 7th” | Date?A specific calendar date or clock time, including deadlines, launch dates, and target dates. | Ananya Sharma | Forge Industries | Aegis / Forge Industries - PCI DSS Comp… 9 Apr 2026 | |
| Event telemetry dashboard work completion | “60% done” | Date?A specific calendar date or clock time, including deadlines, launch dates, and target dates. | Chris Lee | Internal | Detect Reliability - 30-Day Review 7 Apr 2026 | |
| Deployment date of redundant ingestion nodes | “March 24th” | Date?A specific calendar date or clock time, including deadlines, launch dates, and target dates. | Tyler Washington | Internal | Detect Reliability - 30-Day Review 7 Apr 2026 | |
| Circuit breaker pattern production date | “March 29th” | Date?A specific calendar date or clock time, including deadlines, launch dates, and target dates. | Tyler Washington | Internal | Detect Reliability - 30-Day Review 7 Apr 2026 | |
| Comply v2 launch date | “April seventh” | Date?A specific calendar date or clock time, including deadlines, launch dates, and target dates. | Rachel Torres | Trailhead | Aegis / Trailhead Marketplace - Renewal… 5 Apr 2026 | |
| Estimated start of next PCI audit cycle | “late July” | Date?A specific calendar date or clock time, including deadlines, launch dates, and target dates. | Isaac Brennan | Trailhead | Aegis / Trailhead Marketplace - Renewal… 5 Apr 2026 | |
| Comply v2 general availability date | “April 7th” | Date?A specific calendar date or clock time, including deadlines, launch dates, and target dates. | Elena Vasquez | Forge Industries | Support Case #1993 - Forge Industries C… 3 Apr 2026 | |
| Comply v2 customer webinar date | “April 10th” | Date?A specific calendar date or clock time, including deadlines, launch dates, and target dates. | David Kim | Forge Industries | Support Case #1993 - Forge Industries C… 3 Apr 2026 | |
| GA deployment date | “April 7th” | Date?A specific calendar date or clock time, including deadlines, launch dates, and target dates. | Ananya Sharma | Internal | Comply v2 - GA Deployment Plan 1 Apr 2026 | |
| v1 decommission timeline | “two weeks post-GA” | Date?A specific calendar date or clock time, including deadlines, launch dates, and target dates. | Ravi Gupta | Internal | Comply v2 - GA Deployment Plan 1 Apr 2026 |